More links
  • Bursaries
  • Tenders
  • Careers
  • Sponsorships
  • Power Outages
  • News & Watts On!
  • Knowledge Center
  • Annual Reports
  • Downloads
  • Photo Gallery
  • External Links
  • FAQ
  • Site Map
  • exit



  •   Home  About Us   History of NamPower

    The History Of NamPower
    Print this page
    Page 1 2

    Because of its great distances and the general low level of economic development in Namibia, the establishment of a country-wide integrated power supply system only became economically feasible in the mid-sixties.
    Consequently, the Government of the Republic of South Africa decided in 1964 that the greatest contribution the State could make to propel economic development in Namibia would be to utilise the waters of the Kunene River for the generation of electric power and to distribute it, primarily, from Windhoek northwards.


    The South West Africa Water and Electricity Corporation (SWAWEK) was formed on 19 December 1964 as a private and fully affiliated company of the Industrial Development Corporation of the RSA with its prime objectives being the development of the Ruacana Scheme, as it later became known, and the establishment of a transmission system for the distribution of power southwards.
    No development of the Kunene River could however be undertaken without the approval of the Government of Portugal. Negotiations were therefore immediately entered into and at a very early stage in 1964 an agreement was reached wherein the principle of "the best joint utilisation" of the water resources of "rivers of common interest" was accepted. By this was meant "the apportionment by the parties, on a fair and equitable basis, of common water resources within the limits of such resources for the maximum benefit of the respective countries".
    Whilst these negotiations were still being conducted, all probable consumers in SWA were being canvassed for connection to the envisaged scheme. Eventually this was completed and firm assurances with regard to cost of electricity and estimated dates as to when supply would be available were given to municipalities and other instances.
    The negotiations with the Portuguese Government, however, took much longer than was originally and this resulted in SWAWEK finding itself in the situation where it would not be able to honour the commitments it had made to its future consumers if it had to wait any longer on a final agreement with the Portuguese Government.

    Back Top Home

        
     Bursaries | Tenders | Careers | Downloads | Annual Reports | Watts On! | Site Map| FAQ
    Copyright © 2005 - 2009, NamPower